Real PulseDubai off-plan status from the DLD register

Method

How Real Pulse reads the DLD project register

Every figure on Real Pulse comes from the Dubai Land Department (DLD) project register, published through the Dubai open data gateway. Real Pulse reads it every day, keeps each reading, and shows what changed.

Last read from the register: 29 November 2026

DLDProject registerDubai open data gateway
DailyRead every morningpages rebuilt after each read
77Saved readingssince 1 August 2026
723Projects coveredon 29 Nov 2026

Sources

The source is the DLD's register of off-plan (real estate) projects, as served by the Dubai open data gateway. It is read each morning, Dubai time. Two pulls are combined: projects by filed start date (this year's registrations) and projects by filed completion date (earlier registrations that are still due to complete). Together they cover 723 projects on 29 Nov 2026.

The change history uses the readings of the start-date pull saved since 1 August 2026 (77 readings to 29 Nov 2026; there are gaps in August and September 2026, and readings are daily from 3 October 2026). Projects that are only in the completion-date pull have been read daily by Real Pulse since 29 November 2026, and their history starts then.

How each figure is read

Daily updates and change history

After each morning read, the pages are rebuilt from the new figures. A change is any difference in % built, filed completion date, status or escrow between one reading of a project and the next. It is dated to the first reading that shows it, with the previous reading alongside, because on days without a reading the exact day of the change is not known.

The "pace" lines on project pages are plain arithmetic on register figures: the average change in % built per month between two readings, the average since the filed start date, and the average that would be needed to reach 100% by the filed completion date. They are not forecasts of handover.

What "past filed date" means

A project is past its filed date when its filed completion date is earlier than the reading date, the register does not mark it finished or cancelled, and its % built figure is readable and below 100%. It says that the developer's own filed date has gone by. It does not say why, and it is not a finding that a contract was breached. Where the filed completion date equals the filed start date, the project page says so, because the flag then comes from that entry.

What Real Pulse does not do

Corrections

If the register itself is wrong, only the developer or the DLD can correct it; Real Pulse shows the corrected figure at the next daily read and lists the change in the project's history. If Real Pulse has misread or mis-stated a register figure, the page is fixed when the error is found and the read date on the page shows when it was last checked. Real Pulse publishes no contact email.

Who publishes Real Pulse

Real Pulse is published from Dubai, UAE by Arman Anis, who has worked in Dubai real estate for 7 years. It is independent: it is not affiliated with the Dubai Land Department or with any developer.

Dubai, UAE7 years in Dubai real estateIndependent

Data download

The current register figures for the 30 projects tracked at launch are in projects.csv (one row per project: DLD project number, names, developer legal name, area, status, % built, filed dates, past-date flag, escrow, units, registered value, read date and page URL). It is rebuilt with every daily read.

Download projects.csv

Source: DLD project register via the Dubai open data gateway, read 29 November 2026.