Completion date moved
Completion date moved: Dubai projects whose filed date changed
Completion date moved: comparing daily readings of the Dubai Land Department register from 1 August 2026 to 29 November 2026, Real Pulse found 31 changes to a filed completion date across 24 projects. 14 moved the date later and 17 moved it earlier; the median change was 214 days.
Last read from the register: 29 November 2026
Every change, newest first
- The Epoque30 Sep 2029 24 Apr 2028 17 months earlier
- District 5330 Jun 2028 22 Jun 2028 8 days earlier
- Elyra Residences by Enaam30 Mar 2029 30 Sep 2028 6 months earlier
- Zeta15 Nov 2031 15 Sep 2031 2 months earlier
- Zeta15 Nov 2028 15 Nov 2031 36 months later
- The St. Regis Residences30 Sep 2029 19 Oct 2026 35 months earlier
- Avior15 Sep 2031 1 Dec 2031 2 months later
- Binghatti Starfall30 Oct 2027 30 Sep 2028 11 months later
- Zeta1 Feb 2031 15 Nov 2028 26 months earlier
- Elyra Residences by Enaam30 Sep 2028 30 Mar 2029 6 months later
- Zeta15 Sep 2031 1 Feb 2031 7 months earlier
- Volu by Asak31 Dec 2027 30 Jul 2028 6 months later
- Holm Central30 Sep 2029 30 Jun 2028 15 months earlier
- Arche Residence by Evera31 Oct 2028 22 Sep 2026 25 months earlier
- Beachfront Gates 330 Sep 2028 30 May 2029 8 months later
- Sawa Residences28 Mar 2030 12 Jul 2030 3 months later
- Sawa Residences12 Jul 2030 28 Mar 2030 3 months earlier
- Celesto tower 431 Dec 2028 28 Dec 2028 3 days earlier
- Fala by Kasco31 Jul 2028 30 Nov 2028 3 months later
- Holm Central31 Aug 2028 30 Sep 2029 12 months later
- Samana South Haven 231 Mar 2029 30 Jun 2029 2 months later
- Darah Residence30 May 2029 30 Dec 2029 7 months later
- THE BAY interiors by MISSONI29 Sep 2030 30 Sep 2029 11 months earlier
- Tavora Grand by JHK29 Sep 2029 30 Mar 2029 5 months earlier
- Tavora Grand by JHK31 Aug 2028 29 Sep 2029 12 months later
- Weston28 Apr 2029 31 Dec 2028 3 months earlier
- Coventry Living1 Jul 2030 1 Jul 2029 12 months earlier
- Binghatti Spectre31 Mar 2028 31 Dec 2028 9 months later
- Samana Downtown One30 Nov 2029 31 Dec 2029 1 month later
- 24hc1 Jul 2027 30 Mar 2027 3 months earlier
- Azizi Abraham30 Sep 2028 4 Aug 2027 13 months earlier
Projects here with a Real Pulse page
All 31 completion date changes as a table
| The Epoque | Reportage Capital Real Estate Development LLC | Ras Al Khor Industrial First | 0% | 30 Sep 2029 → 24 Apr 2028 on 27 Nov 2026 | Pending |
| District 53 | Modon Company For Real Estate Development LLC | Madinat Al Mataar | 0% | 30 Jun 2028 → 22 Jun 2028 on 20 Nov 2026 | Active |
| Elyra Residences by Enaam | Enaam Properties Development LLC | Nadd Hessa | 0% | 30 Mar 2029 → 30 Sep 2028 on 19 Nov 2026 | Pending |
| Zeta | Acube Zeta Real Estate Development LLC | Wadi Al Safa 2 | 0% | 15 Nov 2031 → 15 Sep 2031 on 17 Nov 2026 | Active |
| Zeta | Acube Zeta Real Estate Development LLC | Wadi Al Safa 2 | 0% | 15 Nov 2028 → 15 Nov 2031 on 13 Nov 2026 | Active |
| The St. Regis Residences Page | Avenew Real Estate Development LLC | Palm Deira | 0% | 30 Sep 2029 → 19 Oct 2026 on 9 Nov 2026 | Active |
| Avior | Acube Avior Real Estate Development LLC | Al Wasl | 0% | 15 Sep 2031 → 1 Dec 2031 on 5 Nov 2026 | Pending |
| Binghatti Starfall | Binghatti Developers FZE | Al Jadaf | 0% | 30 Oct 2027 → 30 Sep 2028 on 29 Oct 2026 | Active |
| Zeta | Acube Zeta Real Estate Development LLC | Wadi Al Safa 2 | 0% | 1 Feb 2031 → 15 Nov 2028 on 21 Oct 2026 | Active |
| Elyra Residences by Enaam | Enaam Properties Development LLC | Nadd Hessa | 0% | 30 Sep 2028 → 30 Mar 2029 on 16 Oct 2026 | Pending |
| Zeta | Acube Zeta Real Estate Development LLC | Wadi Al Safa 2 | 0% | 15 Sep 2031 → 1 Feb 2031 on 16 Oct 2026 | Active |
| Volu by Asak | Asak Real Estate Development LLC | Al Barshaa South Third | 0% | 31 Dec 2027 → 30 Jul 2028 on 14 Oct 2026 | Pending |
| Holm Central | Holm Avenue Real Estate Development LLC | Al Satwa | 0% | 30 Sep 2029 → 30 Jun 2028 on 9 Oct 2026 | Active |
| Arche Residence by Evera Page | Evera Real Estate Development Co. LLC | Madinat Al Mataar | 0% | 31 Oct 2028 → 22 Sep 2026 on 8 Oct 2026 | Pending |
| Beachfront Gates 3 | Dubai South Properties DWC LLC | Madinat Al Mataar | 0% | 30 Sep 2028 → 30 May 2029 on 8 Oct 2026 | Active |
| Sawa Residences | Qube Development LLC | Ras Al Khor Industrial First | 0% | 28 Mar 2030 → 12 Jul 2030 on 8 Oct 2026 | Active |
| Sawa Residences | Qube Development LLC | Ras Al Khor Industrial First | 0% | 12 Jul 2030 → 28 Mar 2030 on 7 Oct 2026 | Active |
| Celesto tower 4 | Tarrad Prime Development LLC | Wadi Al Safa 5 | 0% | 31 Dec 2028 → 28 Dec 2028 on 3 Oct 2026 | Active |
| Fala by Kasco | Kasco Real Estate Development LLC | Al Jadaf | 0% | 31 Jul 2028 → 30 Nov 2028 on 16 Sep 2026 | Active |
| Holm Central | Holm Avenue Real Estate Development LLC | Al Satwa | 0% | 31 Aug 2028 → 30 Sep 2029 on 16 Sep 2026 | Active |
| Samana South Haven 2 | Samana Platinum Real Estate Development LLC | Saih Shuaib 2 | 0% | 31 Mar 2029 → 30 Jun 2029 on 8 Sep 2026 | Active |
| Darah Residence | Darah South Real Estate Development LLC | Madinat Al Mataar | 0% | 30 May 2029 → 30 Dec 2029 on 7 Sep 2026 | Pending |
| THE BAY interiors by MISSONI | Tomorrow World Real Estate Development LLC | Palm Deira | 0% | 29 Sep 2030 → 30 Sep 2029 on 1 Sep 2026 | Active |
| Tavora Grand by JHK | Jhk Heights Real Estate Development LLC | Warsan Fourth | 0% | 29 Sep 2029 → 30 Mar 2029 on 31 Aug 2026 | Pending |
| Tavora Grand by JHK | Jhk Heights Real Estate Development LLC | Warsan Fourth | 0% | 31 Aug 2028 → 29 Sep 2029 on 22 Aug 2026 | Pending |
| Weston | Wadan Real Estate Development LLC | Wadi Al Safa 5 | 0% | 28 Apr 2029 → 31 Dec 2028 on 22 Aug 2026 | Active |
| Coventry Living | Gfs Wonders Developers LLC | Al Barsha South Fourth | 0% | 1 Jul 2030 → 1 Jul 2029 on 17 Aug 2026 | Cancelled |
| Binghatti Spectre | Binghatti Developers FZE | Al Jadaf | 0% | 31 Mar 2028 → 31 Dec 2028 on 7 Aug 2026 | Active |
| Samana Downtown One | Samana Platinum Real Estate Development LLC | Jabal Ali Industrial Second | 0% | 30 Nov 2029 → 31 Dec 2029 on 7 Aug 2026 | Active |
| 24hc | O&f Dhcc Real Estate Development LLC | Um Hurair Second | 80% | 1 Jul 2027 → 30 Mar 2027 on 5 Aug 2026 | Active |
| Azizi Abraham Page | Azizi Developments LLC | Jabal Ali Industrial Second | 2% | 30 Sep 2028 → 4 Aug 2027 on 4 Aug 2026 | Active |
A change is dated to the first reading that shows it. Readings were not daily before 3 October 2026. Click a column to sort; type to filter.
Questions
How many Dubai projects had their completion date moved?
24 projects had a filed completion date change in the DLD register readings between 1 Aug 2026 and 29 Nov 2026, 31 changes in all (some moved more than once).
Are completion dates moved later more often than earlier?
14 of the 31 changes moved the filed date later and 17 moved it earlier. The median change was 214 days.
What was the most recent completion date change?
On 27 Nov 2026 the register showed The Epoque with a filed completion date of 24 Apr 2028 instead of 30 Sep 2029.
Does a new filed date change a buyer's handover date?
The filed completion date is the developer's filing with the DLD. The handover date that binds a developer to a buyer is the one in the sale and purchase agreement.
Which readings does this page use?
The start-date pull of the DLD register saved since 1 Aug 2026 (about 400 projects). Projects outside that pull have no change history before Real Pulse began reading them.
More from the register
Source: DLD project register via the Dubai open data gateway, read 29 November 2026. Method.