Real PulseDubai off-plan status from the DLD register

Completion date moved

Completion date moved: Dubai projects whose filed date changed

Completion date moved: comparing daily readings of the Dubai Land Department register from 1 August 2026 to 29 November 2026, Real Pulse found 31 changes to a filed completion date across 24 projects. 14 moved the date later and 17 moved it earlier; the median change was 214 days.

Last read from the register: 29 November 2026

31Date changes
24Projects
14Moved later
17Moved earlier

Every change, newest first

  1. The Epoque30 Sep 2029 24 Apr 2028 17 months earlier
  2. District 5330 Jun 2028 22 Jun 2028 8 days earlier
  3. Elyra Residences by Enaam30 Mar 2029 30 Sep 2028 6 months earlier
  4. Zeta15 Nov 2031 15 Sep 2031 2 months earlier
  5. Zeta15 Nov 2028 15 Nov 2031 36 months later
  6. The St. Regis Residences30 Sep 2029 19 Oct 2026 35 months earlier
  7. Avior15 Sep 2031 1 Dec 2031 2 months later
  8. Binghatti Starfall30 Oct 2027 30 Sep 2028 11 months later
  9. Zeta1 Feb 2031 15 Nov 2028 26 months earlier
  10. Elyra Residences by Enaam30 Sep 2028 30 Mar 2029 6 months later
  11. Zeta15 Sep 2031 1 Feb 2031 7 months earlier
  12. Volu by Asak31 Dec 2027 30 Jul 2028 6 months later
  13. Holm Central30 Sep 2029 30 Jun 2028 15 months earlier
  14. Arche Residence by Evera31 Oct 2028 22 Sep 2026 25 months earlier
  15. Beachfront Gates 330 Sep 2028 30 May 2029 8 months later
  16. Sawa Residences28 Mar 2030 12 Jul 2030 3 months later
  17. Sawa Residences12 Jul 2030 28 Mar 2030 3 months earlier
  18. Celesto tower 431 Dec 2028 28 Dec 2028 3 days earlier
  19. Fala by Kasco31 Jul 2028 30 Nov 2028 3 months later
  20. Holm Central31 Aug 2028 30 Sep 2029 12 months later
  21. Samana South Haven 231 Mar 2029 30 Jun 2029 2 months later
  22. Darah Residence30 May 2029 30 Dec 2029 7 months later
  23. THE BAY interiors by MISSONI29 Sep 2030 30 Sep 2029 11 months earlier
  24. Tavora Grand by JHK29 Sep 2029 30 Mar 2029 5 months earlier
  25. Tavora Grand by JHK31 Aug 2028 29 Sep 2029 12 months later
  26. Weston28 Apr 2029 31 Dec 2028 3 months earlier
  27. Coventry Living1 Jul 2030 1 Jul 2029 12 months earlier
  28. Binghatti Spectre31 Mar 2028 31 Dec 2028 9 months later
  29. Samana Downtown One30 Nov 2029 31 Dec 2029 1 month later
  30. 24hc1 Jul 2027 30 Mar 2027 3 months earlier
  31. Azizi Abraham30 Sep 2028 4 Aug 2027 13 months earlier

Projects here with a Real Pulse page

All 31 completion date changes as a table

31 rows
The EpoqueReportage Capital Real Estate Development LLCRas Al Khor Industrial First0%30 Sep 2029 → 24 Apr 2028 on 27 Nov 2026Pending
District 53Modon Company For Real Estate Development LLCMadinat Al Mataar0%30 Jun 2028 → 22 Jun 2028 on 20 Nov 2026Active
Elyra Residences by EnaamEnaam Properties Development LLCNadd Hessa0%30 Mar 2029 → 30 Sep 2028 on 19 Nov 2026Pending
ZetaAcube Zeta Real Estate Development LLCWadi Al Safa 20%15 Nov 2031 → 15 Sep 2031 on 17 Nov 2026Active
ZetaAcube Zeta Real Estate Development LLCWadi Al Safa 20%15 Nov 2028 → 15 Nov 2031 on 13 Nov 2026Active
The St. Regis Residences PageAvenew Real Estate Development LLCPalm Deira0%30 Sep 2029 → 19 Oct 2026 on 9 Nov 2026Active
AviorAcube Avior Real Estate Development LLCAl Wasl0%15 Sep 2031 → 1 Dec 2031 on 5 Nov 2026Pending
Binghatti StarfallBinghatti Developers FZEAl Jadaf0%30 Oct 2027 → 30 Sep 2028 on 29 Oct 2026Active
ZetaAcube Zeta Real Estate Development LLCWadi Al Safa 20%1 Feb 2031 → 15 Nov 2028 on 21 Oct 2026Active
Elyra Residences by EnaamEnaam Properties Development LLCNadd Hessa0%30 Sep 2028 → 30 Mar 2029 on 16 Oct 2026Pending
ZetaAcube Zeta Real Estate Development LLCWadi Al Safa 20%15 Sep 2031 → 1 Feb 2031 on 16 Oct 2026Active
Volu by AsakAsak Real Estate Development LLCAl Barshaa South Third0%31 Dec 2027 → 30 Jul 2028 on 14 Oct 2026Pending
Holm CentralHolm Avenue Real Estate Development LLCAl Satwa0%30 Sep 2029 → 30 Jun 2028 on 9 Oct 2026Active
Arche Residence by Evera PageEvera Real Estate Development Co. LLCMadinat Al Mataar0%31 Oct 2028 → 22 Sep 2026 on 8 Oct 2026Pending
Beachfront Gates 3Dubai South Properties DWC LLCMadinat Al Mataar0%30 Sep 2028 → 30 May 2029 on 8 Oct 2026Active
Sawa ResidencesQube Development LLCRas Al Khor Industrial First0%28 Mar 2030 → 12 Jul 2030 on 8 Oct 2026Active
Sawa ResidencesQube Development LLCRas Al Khor Industrial First0%12 Jul 2030 → 28 Mar 2030 on 7 Oct 2026Active
Celesto tower 4Tarrad Prime Development LLCWadi Al Safa 50%31 Dec 2028 → 28 Dec 2028 on 3 Oct 2026Active
Fala by KascoKasco Real Estate Development LLCAl Jadaf0%31 Jul 2028 → 30 Nov 2028 on 16 Sep 2026Active
Holm CentralHolm Avenue Real Estate Development LLCAl Satwa0%31 Aug 2028 → 30 Sep 2029 on 16 Sep 2026Active
Samana South Haven 2Samana Platinum Real Estate Development LLCSaih Shuaib 20%31 Mar 2029 → 30 Jun 2029 on 8 Sep 2026Active
Darah ResidenceDarah South Real Estate Development LLCMadinat Al Mataar0%30 May 2029 → 30 Dec 2029 on 7 Sep 2026Pending
THE BAY interiors by MISSONITomorrow World Real Estate Development LLCPalm Deira0%29 Sep 2030 → 30 Sep 2029 on 1 Sep 2026Active
Tavora Grand by JHKJhk Heights Real Estate Development LLCWarsan Fourth0%29 Sep 2029 → 30 Mar 2029 on 31 Aug 2026Pending
Tavora Grand by JHKJhk Heights Real Estate Development LLCWarsan Fourth0%31 Aug 2028 → 29 Sep 2029 on 22 Aug 2026Pending
WestonWadan Real Estate Development LLCWadi Al Safa 50%28 Apr 2029 → 31 Dec 2028 on 22 Aug 2026Active
Coventry LivingGfs Wonders Developers LLCAl Barsha South Fourth0%1 Jul 2030 → 1 Jul 2029 on 17 Aug 2026Cancelled
Binghatti SpectreBinghatti Developers FZEAl Jadaf0%31 Mar 2028 → 31 Dec 2028 on 7 Aug 2026Active
Samana Downtown OneSamana Platinum Real Estate Development LLCJabal Ali Industrial Second0%30 Nov 2029 → 31 Dec 2029 on 7 Aug 2026Active
24hcO&f Dhcc Real Estate Development LLCUm Hurair Second80%1 Jul 2027 → 30 Mar 2027 on 5 Aug 2026Active
Azizi Abraham PageAzizi Developments LLCJabal Ali Industrial Second2%30 Sep 2028 → 4 Aug 2027 on 4 Aug 2026Active

A change is dated to the first reading that shows it. Readings were not daily before 3 October 2026. Click a column to sort; type to filter.

Questions

How many Dubai projects had their completion date moved?

24 projects had a filed completion date change in the DLD register readings between 1 Aug 2026 and 29 Nov 2026, 31 changes in all (some moved more than once).

Are completion dates moved later more often than earlier?

14 of the 31 changes moved the filed date later and 17 moved it earlier. The median change was 214 days.

What was the most recent completion date change?

On 27 Nov 2026 the register showed The Epoque with a filed completion date of 24 Apr 2028 instead of 30 Sep 2029.

Does a new filed date change a buyer's handover date?

The filed completion date is the developer's filing with the DLD. The handover date that binds a developer to a buyer is the one in the sale and purchase agreement.

Which readings does this page use?

The start-date pull of the DLD register saved since 1 Aug 2026 (about 400 projects). Projects outside that pull have no change history before Real Pulse began reading them.

More from the register

Source: DLD project register via the Dubai open data gateway, read 29 November 2026. Method.