Real PulseDubai off-plan status from the DLD register

Handover by year

Dubai off-plan projects handover 2027

Dubai off-plan projects handover 2027: on 29 November 2026, the Dubai Land Department register lists 38 projects with a filed completion date in 2027. 30 are active, 8 are pending or conditionally activating, 0 are already marked finished. The median % built of the active projects under construction is 8.7%.

Last read from the register: 29 November 2026

38Filed for 2027
0Marked finished
0Past filed date
8.7%Median % built*

Construction progress of the 2027 projects

Number of projects by % built on the register. Bars: 0%, then steps of 10 points.

*Median of the active projects between 0% and 100% built.

Filed completions by month, 2027

2027 projects with a Real Pulse page

6

All 38 projects with a 2027 filed completion date

38 rows
24hcO&f Dhcc Real Estate Development LLCUm Hurair Second80%30 Mar 2027ActiveNo
Binghatti Square 1Binghatti Developers FZEWadi Al Safa 30%30 Jun 2027PendingNo
Binghatti Square 2Binghatti Developers FZEWadi Al Safa 30%30 Jun 2027PendingNo
Binghatti Square 3Binghatti Developers FZEWadi Al Safa 30%30 Jun 2027PendingNo
Nejm 1Danf Developments LLCWadi Al Safa 30%30 Jun 2027ActiveNo
Project MaybachBinghatti Developers FZENad Al Shiba First19.1%30 Jun 2027ActiveNo
Binghatti Luxuria PageBinghatti Developers FZEAl Barsha South Fifth7%30 Jul 2027ActiveNo
Azizi Abraham PageAzizi Developments LLCJabal Ali Industrial Second2%4 Aug 2027ActiveNo
AmaraeBuyut Aljiwar Real Estate Development LLC S.o.cMadinat Al Mataar0%15 Aug 2027PendingNo
Astra ResidencesDugasta Properties Development LLCMadinat Al Mataar15.3%31 Aug 2027ActiveNo
Listone ResidenceLion Stone Properties LLCAl Warsan First0%31 Aug 2027ActiveNo
Maybach Six PageBinghatti Developers FZENad Al Shiba First17.5%31 Aug 2027ActiveNo
Maybach Ultimate Luxury PageBinghatti Developers FZENad Al Shiba First17.7%31 Aug 2027ActiveNo
Symphony by ChaimaaDeval Real Estate Development LLCWadi Al Safa 30%31 Aug 2027ActiveNo
Vista by Vision PageClear Vision Real Estate Development LLCMe'Aisem First12.2%1 Sep 2027ActiveNo
VIVIDA ResidencesN A M O Real Estate Development LLCMadinat Al Mataar0.8%30 Sep 2027ActiveNo
Golf Terrace Residences By ASAKAsak Real Estate Development LLCMe'Aisem First5.1%2 Oct 2027ActiveNo
Cresswell Views IIAdev Properties (br Of Arady Properties - PSC )(dubai Branch )Madinat Al Mataar0%7 Oct 2027PendingNo
Andare HeightsUniestate Properties LLCWadi Al Safa 538.1%15 Oct 2027PendingNo
1wood Residence 2Object One Real Estate Development LLCAl Barsha South Fourth0%20 Oct 2027ActiveNo
Binghatti SkyterracesBinghatti Developers FZEAl Hebiah First7%31 Oct 2027ActiveNo
Derby HeightsA M I S Signature Development LLCWadi Al Safa 310.1%31 Oct 2027ActiveNo
Helvetia VerdeD H G Property Development LLCBukadra0.6%30 Nov 2027ActiveNo
Zazen Acacia ResidencesZazen Property Development LLCMadinat Al Mataar0%30 Nov 2027ActiveNo
Avida ResidencesSerene Marina Real Estate Development LLCPalm Deira6.8%1 Dec 2027ActiveNo
Sea Mirror ResidencesLamar Development LLCJumeirah Second10.4%5 Dec 2027ActiveNo
Route 66Deerfields Real Estate Development LLC S.o.cSaih Shuaib 10%12 Dec 2027ActiveNo
Villa dell ArteAmberton Residences Real Estate LLCPalm Deira0%27 Dec 2027ActiveNo
Binghatti WraithBinghatti Developers FZEAl Jadaf0%30 Dec 2027ActiveNo
Longfor International CenterStar Lang Real Estate Development LLCAl Warsan First1.6%30 Dec 2027ActiveNo
Alder at Park FiveDeyaar Development (p.j.s.c)Me'Aisem First6.1%31 Dec 2027ActiveNo
Babylon TowerHeritage Real Estate Development LLCAl Thanyah First0%31 Dec 2027PendingNo
Binghatti EthereaBinghatti Developers FZEAl Barsha South Fourth7.2%31 Dec 2027ActiveNo
Binghatti Skyflame 1Binghatti Developers FZEWadi Al Safa 315.3%31 Dec 2027ActiveNo
Binghatti Skyflame 2 PageBinghatti Developers FZEWadi Al Safa 312.2%31 Dec 2027ActiveNo
Divine ElementsTakmeel Real Estate Development LLCMadinat Al Mataar0%31 Dec 2027ActiveNo
Jasmine ResidenceDar Comfort Real Estate LLCAl Barsha South Fifth0%31 Dec 2027PendingNo
One By PrestonPreston Properties LLCMadinat Al Mataar0%31 Dec 2027ActiveNo

Sorted by filed completion date. Click a column to sort; type to filter. Projects marked “Page” link to their Real Pulse page.

Questions about handover in 2027

How many Dubai off-plan projects are due for handover in 2027?

The DLD register read on 29 Nov 2026 lists 38 projects with a filed completion date in 2027 (30 active, 8 pending or conditionally activating, 0 finished, 0 cancelled). A filed date is the developer's filing with the DLD, not a contractual handover date.

Which 2027 projects are past their filed completion date?

None of the 38 projects with a 2027 filed date had passed it on 29 Nov 2026.

What is the median construction progress of projects due in 2027?

The median % built of the active 2027 projects between 0% and 100% is 8.7% on the register read on 29 Nov 2026.

Which month of 2027 has the most filed completions?

December 2027 has the most filed completion dates: 14 projects.

How often is the 2027 handover list updated?

Real Pulse reads the DLD register every day; the 2027 list was rebuilt from the reading of 29 Nov 2026 and changes when a filed date, status or % built changes.

More from the register

Source: DLD project register via the Dubai open data gateway, read 29 November 2026. Method.