Project completion percentage in Dubai: what % built means on the DLD register
Project completion percentage in Dubai is the construction figure the Dubai Land Department holds for each project, shown as % built on its register and in Dubai REST. On 29 November 2026 the median among 353 active projects between 0% and 100% was 37.8%, and 171 active projects still showed 0%.
Last read from the register: 29 November 2026
Step by step
- 1It is the DLD’s figureThe register holds one construction percentage per project; Dubai REST shows it on the building image.
- 2See the inspection behind itIn Dubai REST (Project Status, Mashrooi) tap the arrow next to the percentage to open the Inspection Details.
- 3Ask for a completion reportThe DLD FAQ says an investor can obtain a report of the completion percentage from the technical auditor, for a fee.
- 4Expect steps, not a smooth lineThe figure changes when a new reading is recorded. Real Pulse project pages chart every change since 1 August 2026.
% built across projects due 2026–2028
Number of projects by % built on the register. Bars: 0%, then steps of 10 points.
*Median of the active projects between 0% and 100%. “Rose” counts projects whose figure went up by at least 0.5 points over about 30 days of readings.
Try it on a project
All projectsOfficial sources (checked 29 Nov 2026)
- DLD guide: Project Status (Mashrooi) in Dubai REST (PDF)The five official app steps
- DLD: Dubai RESTCompletion percentage, project photos, escrow account number
- DLD: Frequently asked questionsCompletion report, escrow account, cancelled projects
Questions
What is the project completion percentage in Dubai?
It is the construction percentage the Dubai Land Department records for an off-plan project. Real Pulse shows it as % built; Dubai REST shows it on the project's building image.
How is the completion percentage checked?
Dubai REST links the percentage to Inspection Details, and the DLD FAQ says an investor can get a completion report from the technical auditor for a fee.
Can I ask for the completion percentage before paying an instalment?
Yes. According to the DLD FAQ, an investor who receives a payment request from the developer has the right to know the current completion percentage.
What is a typical completion percentage today?
On 29 Nov 2026 the median among 353 active projects between 0% and 100% was 37.8%.
Why has the percentage not changed for months?
The figure only changes when a new value is recorded on the register, so it moves in steps. A flat figure shows that no new value was recorded, not why.
More from the register
Source: DLD project register via the Dubai open data gateway, read 29 November 2026. Method.