Real PulseDubai off-plan status from the DLD register
Portside Square in Dubai Maritime City, Dubai Active

Handover date and construction progress

Portside Square

DLD project no. 4213 · Ellington PCFC MR Development LLC · Madinat Dubai Almelaheyah (Dubai Maritime City)

Filed handover 31 Dec 2029
ActiveEscrow account
DeveloperEllington PCFC MR Development LLCDubai Maritime City, Dubai

Last read from the register: 29 November 2026

Quick answer

On 29 November 2026, the Dubai Land Department register lists Portside Square (DLD project no. 4213) by Ellington PCFC MR Development LLC in Madinat Dubai Almelaheyah (Dubai Maritime City) as active, 0% built, with completion filed for 31 December 2029. That date has not passed: it is 37 months away. An escrow account is registered for it, so buyers' payments are held in an account ring-fenced for construction under Dubai Law No. 8 of 2007.

More detail

Portside Square is active on the register but no construction progress has been recorded yet: the figure is still 0%, 2 months after the filed start date of 1 Sep 2026.

428Units registered
AED 350MRegistered value
1 Sep 2026Filed start date
4213DLD project no.

Schedule vs construction

Filed schedule elapsed7%
Today · 29 Nov 2026
Filed start1 Sep 2026Filed completion31 Dec 2029
% built (register)0%
0%100%
37 months to filed dateFiled schedule 39 months

Plain arithmetic from the register's filed dates and % built, not a forecast.

Register checks

How Portside Square has changed since 1 August 2026

Real Pulse compared 75 readings of the register for Portside Square from 5 Aug 2026 to 29 Nov 2026 and found 2 changes:

No construction recorded in 75 readings since 5 Aug 2026% built has been 0% in every reading to 29 Nov 2026.
  1. Status changed Pending Active
  2. Escrow account shown No Yes
  3. First reading 75 readings to 29 Nov 2026
All changes as a table
Recorded onWhat changedFromToPrevious reading
17 Oct 2026Escrow accountNoYes16 Oct 2026
20 Oct 2026StatusPendingActive19 Oct 2026

Each change is dated to the first reading that shows it; it happened after the previous reading.

Portside Square first appears in the daily readings on 5 Aug 2026, so its history starts there rather than on 1 August 2026.

Pace on the register (arithmetic, not a forecast)

No pace can be worked out for Portside Square yet: the register records 0% built although the filed start date (1 Sep 2026) has passed.

Madinat Dubai Almelaheyah on the register

17Projects on the register
2Past filed date
2.9%Median % built*

Projectsof which past filed datePortside Square’s bin

Projects in Madinat Dubai Almelaheyah by % built, in bins of 10 points (0–10 includes 0%). *Median of 12 active projects between 0% and 100%.

Ellington PCFC MR Development LLC on the register

1Projects
1Active
0Finished
0Past filed date
–Median % built*

Projects filed under the legal name Ellington Pcfc Mr Development LLC. *Median of its 0 active projects between 0% and 100%.

Full register record (all fields)

StatusActive (ACTIVE)
% built0%
Filed completion date31 December 2029
Filed start date1 September 2026
Units428
Registered valueAED 350,000,000
Escrow accountYes, registered
Developer (legal name)ELLINGTON PCFC MR DEVELOPMENT L.L.C
Area (register district)Madinat Dubai Almelaheyah (Dubai Maritime City)
Name on the registerPORTSIDE SQUARE
DLD project no.4213
Register descriptionMixed Use - Residential & with Retails @ ground ( office, retails & restaurant ) 3 residential buildings (shared G+1P+( 3X 16th floors +R) and Amenities Building (G+P+2)

Questions about Portside Square

What is the handover date of Portside Square?

The Dubai Land Department register shows a filed completion date of 31 December 2029 for Portside Square (read 29 Nov 2026). This is the date the developer filed with the DLD, not a contractual handover date; the date in a buyer's sale and purchase agreement is the one that applies to that buyer.

How much of Portside Square is built?

Portside Square is 0% built according to the DLD register on 29 Nov 2026. The figure has not changed since 5 Aug 2026. The DLD sets this figure after inspecting the site.

Is Portside Square delayed?

Not on the register's figures: Portside Square's filed completion date of31 Dec 2029 has not passed, and it did not change in the readings from 5 Aug 2026 to 29 Nov 2026.

Does Portside Square have an escrow account?

Yes. The DLD register shows an escrow account for Portside Square, first shown on 17 Oct 2026. Under Dubai Law No. 8 of 2007, buyers' payments for an off-plan project go into an escrow account ring-fenced for its construction. An escrow account does not guarantee that a project will be completed.

Who is the developer of Portside Square?

The register lists Ellington PCFC MR Development LLC as the developer of Portside Square; the legal name as filed is ELLINGTON PCFC MR DEVELOPMENT L.L.C.

Where is Portside Square?

The register places Portside Square in Madinat Dubai Almelaheyah, the register district for Dubai Maritime City. It is registered with 428 units.

Source: DLD project register via the Dubai open data gateway, read 29 November 2026. Method.