Real PulseDubai off-plan status from the DLD register
Binghatti Hillcrest in Al Barshaa South Third, Dubai Active

Handover date and construction progress

Binghatti Hillcrest

DLD project no. 4105 · Binghatti Developers FZE · Al Barshaa South Third

Filed handover 31 Dec 2026
ActiveEscrow account
DeveloperBinghatti Developers FZEAl Barshaa South Third, Dubai

Last read from the register: 29 November 2026

Quick answer

On 29 November 2026, the Dubai Land Department register lists Binghatti Hillcrest (DLD project no. 4105) by Binghatti Developers FZE in Al Barshaa South Third as active, 60% built, with completion filed for 31 December 2026. That date has not passed: it is 1 month away. An escrow account is registered for it, so buyers' payments are held in an account ring-fenced for construction under Dubai Law No. 8 of 2007.

More detail

Binghatti Hillcrest is under construction on the register at 60%, 40 percentage points short of 100%, on a filed schedule of 14 months from 1 Oct 2025 to 31 Dec 2026 of which 13 months have passed.

396Units registered
AED 135MRegistered value
1 Oct 2025Filed start date
4105DLD project no.

Schedule vs construction

Filed schedule elapsed93%
Today · 29 Nov 2026
Filed start1 Oct 2025Filed completion31 Dec 2026
% built (register)60%
0%100%
1 month to filed dateFiled schedule 14 months

Plain arithmetic from the register's filed dates and % built, not a forecast.

Register checks

How Binghatti Hillcrest has changed since 1 August 2026

Binghatti Hillcrest is outside the register pull that Real Pulse's daily history comes from (saved daily since 1 August 2026), so no dated changes before 29 Nov 2026 are available. Real Pulse has read it daily since 29 Nov 2026; any change in its % built (now 60%), filed completion date (now 31 Dec 2026), status or escrow will be listed here with its date.

  1. First reading 1 reading to 29 Nov 2026

Pace on the register (arithmetic, not a forecast)

In percentage points of % built per month. These are sums on the register's own figures for Binghatti Hillcrest, not a forecast of when it will be handed over. The DLD updates the percentage after site inspections, so it moves in steps rather than smoothly.

Al Barshaa South Third on the register

17Projects on the register
4Past filed date
60%Median % built*

Projectsof which past filed dateBinghatti Hillcrest’s bin

Projects in Al Barshaa South Third by % built, in bins of 10 points (0–10 includes 0%). *Median of 10 active projects between 0% and 100%.

Binghatti Developers FZE on the register

35Projects
29Active
3Finished
12Past filed date
41.4%Median % built*

Projects filed under the legal name Binghatti Developers FZE. *Median of its 22 active projects between 0% and 100%.

Full register record (all fields)

StatusActive (ACTIVE)
% built60%
Filed completion date31 December 2026
Filed start date1 October 2025
Units396
Registered valueAED 135,000,000
Escrow accountYes, registered
Developer (legal name)Binghatti Developers FZE
Area (register district)Al Barshaa South Third
Name on the registerBinghatti Hillcrest
DLD project no.4105
Register descriptionB + G + 4 RESIDENTIAL FLOORS + ROOF

Questions about Binghatti Hillcrest

What is the handover date of Binghatti Hillcrest?

The Dubai Land Department register shows a filed completion date of 31 December 2026 for Binghatti Hillcrest (read 29 Nov 2026). This is the date the developer filed with the DLD, not a contractual handover date; the date in a buyer's sale and purchase agreement is the one that applies to that buyer.

How much of Binghatti Hillcrest is built?

Binghatti Hillcrest is 60% built according to the DLD register on 29 Nov 2026. The DLD sets this figure after inspecting the site.

Is Binghatti Hillcrest delayed?

Not on the register's figures: Binghatti Hillcrest's filed completion date of31 Dec 2026 has not passed. Real Pulse has read it daily only since 29 Nov 2026, so earlier changes to that date are not known.

Does Binghatti Hillcrest have an escrow account?

Yes. The DLD register shows an escrow account for Binghatti Hillcrest. Under Dubai Law No. 8 of 2007, buyers' payments for an off-plan project go into an escrow account ring-fenced for its construction. An escrow account does not guarantee that a project will be completed.

Who is the developer of Binghatti Hillcrest?

The register lists Binghatti Developers FZE as the developer of Binghatti Hillcrest; the legal name as filed is Binghatti Developers FZE.

Where is Binghatti Hillcrest?

The register places Binghatti Hillcrest in Al Barshaa South Third. It is registered with 396 units.

Source: DLD project register via the Dubai open data gateway, read 29 November 2026. Method.