Handover date and construction progress

One by Binghatti

DLD project no. 3107 · Binghatti Developers FZE · Business Bay

Filed handover 30 May 2026
ActiveEscrow account
Past its filed completion date. Filed for 30 May 2026, not marked finished on the register.
DeveloperBinghatti Developers FZEBusiness Bay, Dubai

Last read from the register: 29 November 2026

Quick answer

On 29 November 2026, the Dubai Land Department register lists One by Binghatti (DLD project no. 3107) by Binghatti Developers FZE in Business Bay as active, 50.2% built, with completion filed for 30 May 2026. That date passed 5 months ago and the project is not marked finished, so it is past its filed completion date. An escrow account is registered for it, so buyers' payments are held in an account ring-fenced for construction under Dubai Law No. 8 of 2007.

More detail

One by Binghatti reads 50.2% built 5 months after its filed completion date of 30 May 2026, with 49.8 percentage points still to be recorded. Its filed schedule started on 1 Mar 2024.

783Units registered
AED 544.5MRegistered value
1 Mar 2024Filed start date
3107DLD project no.

Schedule vs construction

Filed schedule elapsed100%
Today · 29 Nov 2026
Filed start1 Mar 2024Filed completion30 May 2026
% built (register)50.2%
0%100%
5 months past filed dateFiled schedule 26 months

Plain arithmetic from the register's filed dates and % built, not a forecast.

Register checks

How One by Binghatti has changed since 1 August 2026

One by Binghatti is outside the register pull that Real Pulse's daily history comes from (saved daily since 1 August 2026), so no dated changes before 29 Nov 2026 are available. Real Pulse has read it daily since 29 Nov 2026; any change in its % built (now 50.2%), filed completion date (now 30 May 2026), status or escrow will be listed here with its date.

  1. First reading 1 reading to 29 Nov 2026

Pace on the register (arithmetic, not a forecast)

In percentage points of % built per month. These are sums on the register's own figures for One by Binghatti, not a forecast of when it will be handed over. The DLD updates the percentage after site inspections, so it moves in steps rather than smoothly.

Business Bay on the register

26Projects on the register
7Past filed date
52.1%Median % built*

Projectsof which past filed dateOne by Binghatti’s bin

Projects in Business Bay by % built, in bins of 10 points (0–10 includes 0%). *Median of 11 active projects between 0% and 100%.

Binghatti Developers FZE on the register

35Projects
29Active
3Finished
12Past filed date
41.4%Median % built*

Projects filed under the legal name Binghatti Developers FZE. *Median of its 22 active projects between 0% and 100%.

Full register record (all fields)

StatusActive (ACTIVE)
% built50.2%
Filed completion date30 May 2026
Filed start date1 March 2024
Units783
Registered valueAED 544,500,000
Escrow accountYes, registered
Developer (legal name)Binghatti Developers FZE
Area (register district)Business Bay
Name on the registerOne by Binghatti
DLD project no.3107
Register description3B + G + 2P + 1 F (AMENITY) + 61 Residential Floors + 1 MECH + 1 MECH(NON-ACCESSIBLE) + Roof.The project designed to have a concrete structure and block with internal and external finishes.

Questions about One by Binghatti

What is the handover date of One by Binghatti?

The Dubai Land Department register shows a filed completion date of 30 May 2026 for One by Binghatti (read 29 Nov 2026). This is the date the developer filed with the DLD, not a contractual handover date; the date in a buyer's sale and purchase agreement is the one that applies to that buyer.

How much of One by Binghatti is built?

One by Binghatti is 50.2% built according to the DLD register on 29 Nov 2026. The DLD sets this figure after inspecting the site.

Is One by Binghatti delayed?

On the register's terms, yes: One by Binghatti's filed completion date of30 May 2026 passed 5 months before 29 Nov 2026 and the project is not marked finished.

Does One by Binghatti have an escrow account?

Yes. The DLD register shows an escrow account for One by Binghatti. Under Dubai Law No. 8 of 2007, buyers' payments for an off-plan project go into an escrow account ring-fenced for its construction. An escrow account does not guarantee that a project will be completed.

Who is the developer of One by Binghatti?

The register lists Binghatti Developers FZE as the developer of One by Binghatti; the legal name as filed is Binghatti Developers FZE.

Where is One by Binghatti?

The register places One by Binghatti in Business Bay. It is registered with 783 units.

Source: DLD project register via the Dubai open data gateway, read 29 November 2026. Method.