Handover date and construction progress
Binghatti Starlight
DLD project no. 3195 · Binghatti Developers FZE · Al Jadaf
Last read from the register: 29 November 2026
Quick answer
- Filed handover 31 Mar 2026passed 7 months ago
- 63.1% builtDLD construction figure
- Escrow account registeredDubai Law No. 8 of 2007
On 29 November 2026, the Dubai Land Department register lists Binghatti Starlight (DLD project no. 3195) by Binghatti Developers FZE in Al Jadaf as active, 63.1% built, with completion filed for 31 March 2026. That date passed 7 months ago and the project is not marked finished, so it is past its filed completion date. An escrow account is registered for it, so buyers' payments are held in an account ring-fenced for construction under Dubai Law No. 8 of 2007.
More detail
Binghatti Starlight reads 63.1% built 7 months after its filed completion date of 31 Mar 2026, with 36.9 percentage points still to be recorded. Its filed schedule started on 30 Jul 2024.
Schedule vs construction
Plain arithmetic from the register's filed dates and % built, not a forecast.
Register checks
- Escrow account registered
- Construction recorded: 63.1% built
- Filed completion date passed (31 Mar 2026)
- Completion date history starts 29 Nov 2026
- Status on register: Active
How Binghatti Starlight has changed since 1 August 2026
Binghatti Starlight is outside the register pull that Real Pulse's daily history comes from (saved daily since 1 August 2026), so no dated changes before 29 Nov 2026 are available. Real Pulse has read it daily since 29 Nov 2026; any change in its % built (now 63.1%), filed completion date (now 31 Mar 2026), status or escrow will be listed here with its date.
-
First reading 1 reading to 29 Nov 2026
Pace on the register (arithmetic, not a forecast)
- 2.3 pts/monthAverage since filed start
- 36.9 ptsPoints left, date passed
In percentage points of % built per month. These are sums on the register's own figures for Binghatti Starlight, not a forecast of when it will be handed over. The DLD updates the percentage after site inspections, so it moves in steps rather than smoothly.
Al Jadaf on the register
Projectsof which past filed dateBinghatti Starlight’s bin
Projects in Al Jadaf by % built, in bins of 10 points (0–10 includes 0%). *Median of 8 active projects between 0% and 100%.
Binghatti Developers FZE on the register
Projects filed under the legal name Binghatti Developers FZE. *Median of its 22 active projects between 0% and 100%.
Full register record (all fields)
| Status | Active (ACTIVE) |
|---|---|
| % built | 63.1% |
| Filed completion date | 31 March 2026 |
| Filed start date | 30 July 2024 |
| Units | 511 |
| Registered value | AED 228,859,115 |
| Escrow account | Yes, registered |
| Developer (legal name) | Binghatti Developers FZE |
| Area (register district) | Al Jadaf |
| Name on the register | Binghatti Starlight |
| DLD project no. | 3195 |
| Register description | 3B + G + 3P + 20 RESIDENTIAL FLOORS + ROOF |
Questions about Binghatti Starlight
What is the handover date of Binghatti Starlight?
The Dubai Land Department register shows a filed completion date of 31 March 2026 for Binghatti Starlight (read 29 Nov 2026). This is the date the developer filed with the DLD, not a contractual handover date; the date in a buyer's sale and purchase agreement is the one that applies to that buyer.
How much of Binghatti Starlight is built?
Binghatti Starlight is 63.1% built according to the DLD register on 29 Nov 2026. The DLD sets this figure after inspecting the site.
Is Binghatti Starlight delayed?
On the register's terms, yes: Binghatti Starlight's filed completion date of31 Mar 2026 passed 7 months before 29 Nov 2026 and the project is not marked finished.
Does Binghatti Starlight have an escrow account?
Yes. The DLD register shows an escrow account for Binghatti Starlight. Under Dubai Law No. 8 of 2007, buyers' payments for an off-plan project go into an escrow account ring-fenced for its construction. An escrow account does not guarantee that a project will be completed.
Who is the developer of Binghatti Starlight?
The register lists Binghatti Developers FZE as the developer of Binghatti Starlight; the legal name as filed is Binghatti Developers FZE.
Where is Binghatti Starlight?
The register places Binghatti Starlight in Al Jadaf. It is registered with 511 units.
Source: DLD project register via the Dubai open data gateway, read 29 November 2026. Method.