Real PulseDubai off-plan status from the DLD register
Binghatti Skyhall in Business Bay, Dubai ActivePast filed date

Handover date and construction progress

Binghatti Skyhall

DLD project no. 3504 · Binghatti Developers FZE · Business Bay

Filed handover 31 Aug 2026
ActiveEscrow account
Past its filed completion date. Filed for 31 Aug 2026, not marked finished on the register.
DeveloperBinghatti Developers FZEBusiness Bay, Dubai

Last read from the register: 29 November 2026

Quick answer

On 29 November 2026, the Dubai Land Department register lists Binghatti Skyhall (DLD project no. 3504) by Binghatti Developers FZE in Business Bay as active, 31.1% built, with completion filed for 31 August 2026. That date passed 2 months ago and the project is not marked finished, so it is past its filed completion date. An escrow account is registered for it, so buyers' payments are held in an account ring-fenced for construction under Dubai Law No. 8 of 2007.

More detail

Binghatti Skyhall reads 31.1% built 2 months after its filed completion date of 31 Aug 2026, with 68.9 percentage points still to be recorded. Its filed schedule started on 1 Feb 2025.

728Units registered
AED 385MRegistered value
1 Feb 2025Filed start date
3504DLD project no.

Schedule vs construction

Filed schedule elapsed100%
Today · 29 Nov 2026
Filed start1 Feb 2025Filed completion31 Aug 2026
% built (register)31.1%
0%100%
2 months past filed dateFiled schedule 18 months

Plain arithmetic from the register's filed dates and % built, not a forecast.

Register checks

How Binghatti Skyhall has changed since 1 August 2026

Binghatti Skyhall is outside the register pull that Real Pulse's daily history comes from (saved daily since 1 August 2026), so no dated changes before 29 Nov 2026 are available. Real Pulse has read it daily since 29 Nov 2026; any change in its % built (now 31.1%), filed completion date (now 31 Aug 2026), status or escrow will be listed here with its date.

  1. First reading 1 reading to 29 Nov 2026

Pace on the register (arithmetic, not a forecast)

In percentage points of % built per month. These are sums on the register's own figures for Binghatti Skyhall, not a forecast of when it will be handed over. The DLD updates the percentage after site inspections, so it moves in steps rather than smoothly.

Business Bay on the register

26Projects on the register
7Past filed date
52.1%Median % built*

Projectsof which past filed dateBinghatti Skyhall’s bin

Projects in Business Bay by % built, in bins of 10 points (0–10 includes 0%). *Median of 11 active projects between 0% and 100%.

Binghatti Developers FZE on the register

35Projects
29Active
3Finished
12Past filed date
41.4%Median % built*

Projects filed under the legal name Binghatti Developers FZE. *Median of its 22 active projects between 0% and 100%.

Full register record (all fields)

StatusActive (ACTIVE)
% built31.1%
Filed completion date31 August 2026
Filed start date1 February 2025
Units728
Registered valueAED 385,000,000
Escrow accountYes, registered
Developer (legal name)Binghatti Developers FZE
Area (register district)Business Bay
Name on the registerBinghatti Skyhall
DLD project no.3504
Register description3B + G + 3P + 29 RESIDENTIAL FLOORS + 1MECH. + ROOF

Questions about Binghatti Skyhall

What is the handover date of Binghatti Skyhall?

The Dubai Land Department register shows a filed completion date of 31 August 2026 for Binghatti Skyhall (read 29 Nov 2026). This is the date the developer filed with the DLD, not a contractual handover date; the date in a buyer's sale and purchase agreement is the one that applies to that buyer.

How much of Binghatti Skyhall is built?

Binghatti Skyhall is 31.1% built according to the DLD register on 29 Nov 2026. The DLD sets this figure after inspecting the site.

Is Binghatti Skyhall delayed?

On the register's terms, yes: Binghatti Skyhall's filed completion date of31 Aug 2026 passed 2 months before 29 Nov 2026 and the project is not marked finished.

Does Binghatti Skyhall have an escrow account?

Yes. The DLD register shows an escrow account for Binghatti Skyhall. Under Dubai Law No. 8 of 2007, buyers' payments for an off-plan project go into an escrow account ring-fenced for its construction. An escrow account does not guarantee that a project will be completed.

Who is the developer of Binghatti Skyhall?

The register lists Binghatti Developers FZE as the developer of Binghatti Skyhall; the legal name as filed is Binghatti Developers FZE.

Where is Binghatti Skyhall?

The register places Binghatti Skyhall in Business Bay. It is registered with 728 units.

Source: DLD project register via the Dubai open data gateway, read 29 November 2026. Method.