Real PulseDubai off-plan status from the DLD register
Binghatti HillsideNo image published ActivePast filed date

Handover date and construction progress

Binghatti Hillside

DLD project no. 3481 · Binghatti Developers FZE · Al Barshaa South Second

Filed handover 30 Jun 2026
ActiveEscrow account
Past its filed completion date. Filed for 30 Jun 2026, not marked finished on the register.
DeveloperBinghatti Developers FZEAl Barshaa South Second, Dubai

Last read from the register: 29 November 2026

Quick answer

On 29 November 2026, the Dubai Land Department register lists Binghatti Hillside (DLD project no. 3481) by Binghatti Developers FZE in Al Barshaa South Second as active, 80% built, with completion filed for 30 June 2026. That date passed 4 months ago and the project is not marked finished, so it is past its filed completion date. An escrow account is registered for it, so buyers' payments are held in an account ring-fenced for construction under Dubai Law No. 8 of 2007.

More detail

Binghatti Hillside reads 80% built 4 months after its filed completion date of 30 Jun 2026, with 20 percentage points still to be recorded. Its filed schedule started on 31 Jan 2025.

411Units registered
AED 150MRegistered value
31 Jan 2025Filed start date
3481DLD project no.

Schedule vs construction

Filed schedule elapsed100%
Today · 29 Nov 2026
Filed start31 Jan 2025Filed completion30 Jun 2026
% built (register)80%
0%100%
4 months past filed dateFiled schedule 16 months

Plain arithmetic from the register's filed dates and % built, not a forecast.

Register checks

How Binghatti Hillside has changed since 1 August 2026

Binghatti Hillside is outside the register pull that Real Pulse's daily history comes from (saved daily since 1 August 2026), so no dated changes before 29 Nov 2026 are available. Real Pulse has read it daily since 29 Nov 2026; any change in its % built (now 80%), filed completion date (now 30 Jun 2026), status or escrow will be listed here with its date.

  1. First reading 1 reading to 29 Nov 2026

Pace on the register (arithmetic, not a forecast)

In percentage points of % built per month. These are sums on the register's own figures for Binghatti Hillside, not a forecast of when it will be handed over. The DLD updates the percentage after site inspections, so it moves in steps rather than smoothly.

Al Barshaa South Second on the register

5Projects on the register
3Past filed date
50.5%Median % built*

Projectsof which past filed dateBinghatti Hillside’s bin

Projects in Al Barshaa South Second by % built, in bins of 10 points (0–10 includes 0%). *Median of 3 active projects between 0% and 100%.

Binghatti Developers FZE on the register

35Projects
29Active
3Finished
12Past filed date
41.4%Median % built*

Projects filed under the legal name Binghatti Developers FZE. *Median of its 22 active projects between 0% and 100%.

Full register record (all fields)

StatusActive (ACTIVE)
% built80%
Filed completion date30 June 2026
Filed start date31 January 2025
Units411
Registered valueAED 150,000,000
Escrow accountYes, registered
Developer (legal name)Binghatti Developers FZE
Area (register district)Al Barshaa South Second
Name on the registerBinghatti Hillside
DLD project no.3481
Register description3B + G + 2P +21 RESIDENTIAL FLOORS + ROOF

Questions about Binghatti Hillside

What is the handover date of Binghatti Hillside?

The Dubai Land Department register shows a filed completion date of 30 June 2026 for Binghatti Hillside (read 29 Nov 2026). This is the date the developer filed with the DLD, not a contractual handover date; the date in a buyer's sale and purchase agreement is the one that applies to that buyer.

How much of Binghatti Hillside is built?

Binghatti Hillside is 80% built according to the DLD register on 29 Nov 2026. The DLD sets this figure after inspecting the site.

Is Binghatti Hillside delayed?

On the register's terms, yes: Binghatti Hillside's filed completion date of30 Jun 2026 passed 4 months before 29 Nov 2026 and the project is not marked finished.

Does Binghatti Hillside have an escrow account?

Yes. The DLD register shows an escrow account for Binghatti Hillside. Under Dubai Law No. 8 of 2007, buyers' payments for an off-plan project go into an escrow account ring-fenced for its construction. An escrow account does not guarantee that a project will be completed.

Who is the developer of Binghatti Hillside?

The register lists Binghatti Developers FZE as the developer of Binghatti Hillside; the legal name as filed is Binghatti Developers FZE.

Where is Binghatti Hillside?

The register places Binghatti Hillside in Al Barshaa South Second. It is registered with 411 units.

Source: DLD project register via the Dubai open data gateway, read 29 November 2026. Method.