Real PulseDubai off-plan status from the DLD register
Callista by ZoyaNo image published Pending

Handover date and construction progress

Callista by Zoya

DLD project no. 4598 · Zoya One Real Estate Developments LLC · Madinat Al Mataar (Dubai South)

Filed handover 31 Oct 2028
PendingNo escrow account
DeveloperZoya One Real Estate Developments LLCDubai South, Dubai

Last read from the register: 29 November 2026

Quick answer

On 29 November 2026, the Dubai Land Department register lists Callista by Zoya (DLD project no. 4598) by Zoya One Real Estate Developments LLC in Madinat Al Mataar (Dubai South) as pending, 0% built, with completion filed for 31 October 2028. That date has not passed: it is 23 months away. No escrow account is registered for it yet; under Dubai Law No. 8 of 2007 a developer needs one before selling units off-plan.

More detail

Callista by Zoya has not started on the register: it is pending with 0% recorded, and its filed start date of 1 Nov 2026 has already passed.

–Units registered
AED 30MRegistered value
1 Nov 2026Filed start date
4598DLD project no.

Schedule vs construction

Filed schedule elapsed4%
Today · 29 Nov 2026
Filed start1 Nov 2026Filed completion31 Oct 2028
% built (register)0%
0%100%
23 months to filed dateFiled schedule 23 months

Plain arithmetic from the register's filed dates and % built, not a forecast.

Register checks

How Callista by Zoya has changed since 1 August 2026

Nothing changed for Callista by Zoya between 6 Oct 2026 and 29 Nov 2026 across 55 readings of the register: it stayed pending at 0% built, with completion filed for 31 Oct 2028 and no escrow account throughout.

  1. First reading 55 readings to 29 Nov 2026

Callista by Zoya first appears in the daily readings on 6 Oct 2026, so its history starts there rather than on 1 August 2026.

Pace on the register (arithmetic, not a forecast)

No pace can be worked out for Callista by Zoya yet: the register records 0% built although the filed start date (1 Nov 2026) has passed.

Madinat Al Mataar on the register

75Projects on the register
11Past filed date
27.9%Median % built*

Projectsof which past filed dateCallista by Zoya’s bin

Projects in Madinat Al Mataar by % built, in bins of 10 points (0–10 includes 0%). *Median of 32 active projects between 0% and 100%.

Zoya One Real Estate Developments LLC on the register

7Projects
5Active
0Finished
0Past filed date
0.8%Median % built*

Projects filed under the legal name Zoya One Real Estate Developments LLC. *Median of its 1 active projects between 0% and 100%.

Full register record (all fields)

StatusPending (PENDING)
% built0%
Filed completion date31 October 2028
Filed start date1 November 2026
UnitsNone registered yet
Registered valueAED 30,000,000
Escrow accountNo escrow account registered
Developer (legal name)ZOYA ONE REAL ESTATE DEVELOPMENTS L.L.C
Area (register district)Madinat Al Mataar (Dubai South)
Name on the registerCallista by Zoya
DLD project no.4598
Register descriptionG+4

Questions about Callista by Zoya

What is the handover date of Callista by Zoya?

The Dubai Land Department register shows a filed completion date of 31 October 2028 for Callista by Zoya (read 29 Nov 2026). This is the date the developer filed with the DLD, not a contractual handover date; the date in a buyer's sale and purchase agreement is the one that applies to that buyer.

How much of Callista by Zoya is built?

Callista by Zoya is 0% built according to the DLD register on 29 Nov 2026. The figure has not changed since 6 Oct 2026. The DLD sets this figure after inspecting the site.

Is Callista by Zoya delayed?

Not on the register's figures: Callista by Zoya's filed completion date of31 Oct 2028 has not passed, and it did not change in the readings from 6 Oct 2026 to 29 Nov 2026.

Does Callista by Zoya have an escrow account?

Not yet. The DLD register shows no escrow account for Callista by Zoya on 29 Nov 2026. Under Dubai Law No. 8 of 2007, buyers' payments for an off-plan project go into an escrow account ring-fenced for its construction. An escrow account does not guarantee that a project will be completed.

Who is the developer of Callista by Zoya?

The register lists Zoya One Real Estate Developments LLC as the developer of Callista by Zoya; the legal name as filed is ZOYA ONE REAL ESTATE DEVELOPMENTS L.L.C.

Where is Callista by Zoya?

The register places Callista by Zoya in Madinat Al Mataar, the register district for Dubai South. No unit count is registered yet.

Source: DLD project register via the Dubai open data gateway, read 29 November 2026. Method.